25.4 2011 05:00
25.4 2011 06:00
25.4 2011 07:00
25.4 2011 08:00
25.4 2011 09:00
25.4 2011 10:00
Temporary shift to diesel generator for
pumps for water injection water to reactors
to allow the connection of the high voltage power panel
of Unit 1/2 and Unit 5/6
25.4 2011 10:57
25.4 2011 11:00
25.4 2011 12:00
The pump of the residual heat removal
system for unit 5 temporarily stopped
25.4 2011 12:22
25.4 2011 13:00
25.4 2011 14:00
Pump for nitrogen injection to unit 1
temporarily stopped
25.4 2011 14:10
25.4 2011 15:00
25.4 2011 16:00
25.4 2011 17:00
25.4 2011 18:00
Water spray to SFP4, concrete pump25.4 2011 18:15-26.4 2011 00:26
25.4 2011 19:00