![]() | 30.3 2011 05:00 |
![]() | 30.3 2011 06:00 |
![]() | 30.3 2011 07:00 |
![]() | 30.3 2011 08:00 |
![]() | 30.3 2011 09:00 |
Start water injection to SFP2, motor driven/fire fighting pump | 30.3 2011 09:25-13:10 |
![]() | 30.3 2011 10:00 |
![]() | 30.3 2011 11:00 |
![]() | 30.3 2011 12:00 |
![]() | 30.3 2011 13:00 |
![]() | 30.3 2011 14:00 |
Water spray to SFP4, concrete pump | 30.3 2011 14:04-18:33 |
![]() | 30.3 2011 15:00 |
![]() | 30.3 2011 16:00 |
![]() | 30.3 2011 17:00 |
![]() | 30.3 2011 18:00 |
![]() | 30.3 2011 19:00 |
Water injection to SFP2 | 30.3 2011 19:05-23:50 |