Since April 1st Tepco has conducted sprayings to bind radioactive dust. These efforts have been concentrated on the slopes behind the two buildings 'across the street' from unit 3 and 4: the Common Spent Fuel Pool (CSFP) and the Medium Voltage Switchyard (MSV) respectively, and to the area around the Central Radwaste Treatment Facility (CHWTF), which is situated to the south of unit 4. From April 24th, spraying was extended to slopes at reactor building 5, the main building and the gymnasium. --------------------------------------------------------------------------------- 16 May 2011: area nearby Solid Waste Storing Facility, conventional method 15 May 2011: 7000 m² area nearby Solid Waste Storing Facility, conventional method 14 May 2011: 7000 m² area east to turbine building 2 using unmanned crawler truck 14 May 2011: area nearby Solid Waste Storing Facility, conventional method 13 May 2011: 7000 m² area nearby Solid Waste Storing Facility, conventional method 13 May 2011: area north and east to unit 1 using unmanned crawler truck 12 May 2011: 5250 m² area nearby Solid Waste Storing Facility, conventional method 11 May 2011: 5250 m² area nearby Solid Waste Storing Facility, conventional method 10 May 2011: 5050 m² area nearby Solid Waste Storing Facility, conventional method 10 May 2011: 6000 m² area eastof turbine building 1, using umnanned crawler truck 9 May 2011: 5250 m² area nearby Solid Waste Storing Facility, conventional method 9 May 2011: area including the west side of Shallow Draft Quay using conventional method 8 May 2011: area including the mountain side of Shallow Draft Quay using conventional method 7 May 2011: 5150 m² area including the mountain side of Shallow Draft Quay using conventional method 6 May 2011: 4000 m² on the west side of the Unit 1 reactor building using unmanned crawler dump truck. 6 May 2011: area including the mountain side of Shallow Draft Quay using conventional method 4 May 2011: 4000 m² area west side of unit 3 using unmanned crawler dump truck 4 May 2011: 5200 m² slope around former Administration Office Building using conventional method 3 May 2011: 4000 m² area west side of unit 3 using unmanned crawler dump truck 3 May 2011: 5300 m² slope around former Administration Office Building using conventional method 2 May 2011: 4000 m² area south and west side of unit 4 using unmanned crawler dump truck 2 May 2011: 5500 m² slope around former Administration Office Building using conventional method 1 May 2011: ? m² at mountainside of the former Administration Office Building using conventional method 1 May 2011: 1000 m² at south side of Unit 4 reactor building using unmanned crawler dump truck 29 April 2011: 7000 m² at east side of Unit 4 turbine building using unmanned crawler dump truck 29 April 2011: 5800 m² at mountainside of Unit 5 using unmanned crawler dump truck 26 April 2011: ? m² coastal side of units 1 to 4 using unmanned crawler dump truck 25 April 2011: 3800 m² mountain side at reactor building 5, slope in front of the main building, and gymnasium building 24 April 2011: 860 m² mountain side at reactor building 5 21 April 2011: 1300 m² mountain side at the CSFP 21 April 2011: 5100 m2 mountainside at MVS 20 April 2011: 1900 m² around the CHWTF 18 April 2011: 1200 m² at the CHWTF 17 April 2011: ? m² at the CHWTF 16 April 2011: 1800 m² mountainside at the CSFP 15 April 2011: 1900 m² mountainside at the CSFP 13 April 2011: 1600 m² mountainside at the CSFP 11 April 2011: 1200 m² mountainside at the CSFP 8 April 2011: 680 m² mountainside at the CSFP 5 April 2011: 550 m² east and south mountainside at the CSFP 1 April 2011: 500 m² mountainside at the CSFP